< Back to Listing HOME > NEWS > New tube type conveyor system installed at Ferrybridge

New tube type conveyor system installed at Ferrybridge
1st August 2008

New tube type conveyor system installed at Ferrybridge Ferry Bridge Conveyors

In October 2007, Lentjes UK awarded Wright Brothers the contract to install the Limestone and Gypsum Handling Conveyors for the Fluidised Gas Desulphurisation Installation at Ferrybridge Power station.

The contract required us to install the free issue pipe conveyors that take the limestone from the rail unloading station into the power station, and the gypsum from the power station to the new Lafarge Plasterboard factory.

The conveyors are 361 metres long (Limestone) and 430 metres long (Gypsum).

We installed the conveyors on an extremely congested site, alongside and over railway lines, roadways and buildings without any incidents or accidents, over a 7 month period. Our site management team worked with client management to ensure a smooth installation, integrating our needs and those of the many other contractors on site.

The installation necessitated many large crane lifts, the largest being a tandem lift for the Limestone conveyor head end.  Wright Brothers staff planned and executed the lift employing 500t and 450t capacity cranes to lift the 30t head end structure and land it on top of a silo 40m in height.  Our site teams are fully qualified as appointed persons, banks men and slingers, enabling us to plan and supervise our own lifts without the need for contract lifts by crane operating companies.

Our client was so pleased with our performance at Ferrybridge that we were invited to tender for the equivalent installations at Fiddlers Ferry and Rugeley Power stations.  Wright Brothers won these contracts and we are now installing the conveyor systems at both these sites.

 

Other News in Date Order

Limestone milk batching plant at Ferrybridge Power Station
29th December 2008

Sugar storage silos installation for Tate & Lyle
14th August 2008

New tube type conveyor system installed at Ferrybridge
1st August 2008

New Cement Storage Silo for Monier Lifetile
18th February 2008

More news on current Wright projects
27th September 2007

The Wright Way to Make Operating Easier at Tarmac Tunstead
3rd September 2007

Wright Engineering at Hillhead 2007
31st May 2007

Wright on track!
30th April 2007

Wright Engineering at the SED Exhibition 2007
31st January 2007

Lafarge Invest in new Roof Tile Collator.
31st January 2007

New Aggregate Storage Hoppers and Conveying System For Lafarge
1st December 2006

Wright Engineering complete Lafarge - Whitwell Quarry Project.
20th November 2006

New Ship Loader Cabin for Foster Yeoman at Glensanda.
3rd August 2006

Safety first at Wright Engineering
27th April 2006

Further success for Wright in Florida.
1st March 2006

Scunthorpe metal recovery plant.
8th January 2006

New Conveyor System for British Gypsum.
14th November 2005

Larger production facilities for Wright Engineering.
9th November 2005

Monier Lifetile picks the Wright System.
19th May 2004

Wright Completes Goonvean Conveyor System.
18th May 2004

New Mill Building for Lafarge - West Thurrock
8th December 2003

Wright Supply New Tile Embossing Machine.
7th January 2002

New Aggregate Storage Hopper for Aggregate Industries.
5th March 2001

Wright Replace Conveyor System for British Gypsum - Robertsbridge
22nd January 2001

New Aggregate In-Feed System for Redland Roofing Systems.
6th March 2000

New Aggregate Cement and Additive Supply Systems for Shawell Works.
14th February 2000

Wright Deliver Japanese Plant!
25th March 1998