Huge project for Tarmac Tunstead rolls into production!
2nd March 2009

Wright Engineering have just commenced a 30 week project for Tarmac at their Tunstead operations. The project involves the installation of Maertz kilns, conveyor systems, transfer towers and screens. On completion Wright Engineering will effect the commissioning process.

LATEST UPDATE 21 July 2009

The installation of the Stone and Lime handling conveyors and associated equipment is now well underway on site.

Our installation team is likely to exceed 30 engineers over the next few weeks.  This workforce is necessary to ensure that the clients timescale requirements will be successfully met, and the new Kiln will be fed with stone for commissioning at the end of September 2009.

The site installation management team is operating under full CDM Regulations and the client has been supplied with all necessary Health and Safety Documentation.  Our in house Health and Safety Manager is performing regular site audits to ensure the project is conducted safely.

 

Other News in Date Order

Expansion of existing workshop.
23rd November 2009

New headquarters building provides further expansion for Wright Engineering.
21st July 2009

Limestone milk batching plant at Ferrybridge Power Station
21st July 2009

Wright Engineering support the W2R Waste recycling Partnership.
21st July 2009

New operator cabin for rail unloading system at Cottam Power Station
6th March 2009

Upgrade for Lafarge Cement UK at their Cauldon Works.
4th March 2009

Huge project for Tarmac Tunstead rolls into production!
2nd March 2009

Sugar storage silos installation for Tate & Lyle
14th August 2008

New tube type conveyor system installed at Ferrybridge
1st August 2008

New Cement Storage Silo for Monier Lifetile
18th February 2008

More news on current Wright projects
27th September 2007

The Wright Way to Make Operating Easier at Tarmac Tunstead
3rd September 2007

Wright Engineering at Hillhead 2007
31st May 2007

Wright on track!
30th April 2007

Wright Engineering at the SED Exhibition 2007
31st January 2007

Lafarge Invest in new Roof Tile Collator.
31st January 2007

New Aggregate Storage Hoppers and Conveying System For Lafarge
1st December 2006

Wright Engineering complete Lafarge - Whitwell Quarry Project.
20th November 2006

New Ship Loader Cabin for Foster Yeoman at Glensanda.
3rd August 2006

Safety first at Wright Engineering
27th April 2006

Further success for Wright in Florida.
1st March 2006

Scunthorpe metal recovery plant.
8th January 2006

New Conveyor System for British Gypsum.
14th November 2005

Larger production facilities for Wright Engineering.
9th November 2005

Monier Lifetile picks the Wright System.
19th May 2004

Wright Completes Goonvean Conveyor System.
18th May 2004

New Mill Building for Lafarge - West Thurrock
8th December 2003

Wright Supply New Tile Embossing Machine.
7th January 2002

New Aggregate Storage Hopper for Aggregate Industries.
5th March 2001

Wright Replace Conveyor System for British Gypsum - Robertsbridge
22nd January 2001

New Aggregate In-Feed System for Redland Roofing Systems.
6th March 2000

New Aggregate Cement and Additive Supply Systems for Shawell Works.
14th February 2000

Wright Deliver Japanese Plant!
25th March 1998