Project Details
- Client: Hitachi Zoven Innova
- Contract Name: Installation of Laser Platforms
- Contract Value: 30k
- Contract Duration: Two weeks
Project Description
Wright Engineering has completed the transportation and installation of three laser platforms into a waster bunker.
Detailed calculations were carried out to ensure that the roof structure was able to support the load beams that were being lifted. The materials were transported to the waste bunker via an electric hoist and the platforms were pre-assembled within the bunker and skated into a final position.
Despite its low value, this was a complex job that required significant expertise and know-how in order to complete it.