Tarmac

Tarmac - Torcoed Quarry Crusher Refurbishment

Tarmac Photo Gallery

Client
Tarmac
Contract Name
Torcoed Quarry Crusher Refurbishment
Contract Value
£39,000
Contract Duration
2 weeks
PROJECT DETAILS

Wright engineering have completed the first phase of a primary crusher refurbishment for Tarmac. Planned over the Christmas shutdown the window to carry out the works was very tight and Wright Engineering supplied labour on days and nights to ensure the works were completed on time for the plant to start up again immediately after the Christmas break.

As can happen often when refurbishing old equipment, once the team started to strip the crusher down it became apparent several other components required replacement. These items were measured on site and quickly sent back to our main facility to manufacture several tonnes of steel work over the Christmas period to ensure no delay to the scheduled shutdown duration.

Contact Wright Engineering